Thursday, November 13, 2014

Loop 375 Extension Now Called 'Border West Expressway'

State and local officials held a groundbreaking this week for the now renamed Border West Expressway project in West El Paso. The project, formerly known as Border Highway West, will create a tolled expressway and complete the loop around the city.
The Border West Expressway will be a tollway for 5.6 miles from West El Paso near Sunland Park to Downtown. (TXDOT)

The largest part of the 7.4 mile project will be the construction of a four-lane tollway stretching from Racetrack Drive on the West Side to Loop 375's current terminus at Santa Fe Street south of Downtown El Paso. Racetrack Drive is located along Paisano Drive just south of Interstate 10 in the vicinity of Sunland Park Drive.

Tuesday, May 27, 2014

Toll Rates Revealed for Border Highway West

State Holds Public Hearing to Discuss Project Financing, Tolling

The colossal Border Highway West project is still years from opening to the public, but Texas Department of Transportation (TXDOT) officials have already determined the rates that commuters will have to pay to drive on the tollway. Officials held a meeting on Tuesday to disclose this and other financial details to the public.
Commuters on the Border Highway West extension in El Paso will pay $1.12 to drive the entire distance when it opens in 2018. (TXDOT)

At the onset, drivers will be charged $1.12 during “peak” hours to drive the entire 5.6-mile distance from Racetrack Drive to Loop 375’s current terminus at Santa Fe Street south of Downtown El Paso, with rates lowering to $0.76 and $0.50 for driving through shorter portions of the highway. The published rates are in 2014 dollars and could be adjusted for inflation once tolls go live. TXDOT officials expect project completion in early 2018.

Weekly Edition, Issue 55

The Weekly Edition, Issue 55 has arrived! Take a look at the newest issue of our Weekly Edition, by clicking HERE. (Note: The newsletter will open in PDF format.)

In this edition:

Don't forget to sign up to be notified when each week's new issue is available. Subscribe below.

Subscribe to our mailing list
* indicates required

Tuesday, February 11, 2014

Transportation Update: Border Highway West

Commission Approves $600M Minute Order for Loop 375 Extension

A minute order was recently signed by the Texas Transportation Commission approving a $600 million grant for the Border Highway West project in El Paso, with funds coming from Texas Mobility Fund bonds. The new tollway will extend Loop 375 from south of Downtown to the northwest for seven additional miles.
The Border Highway West extension will include new accessibility to and from both Doniphan Drive and McNutt Road near Sunland Park, New Mexico. (TXDOT)

The funds have been authorized for the Camino Real Regional Mobility Authority (CRRMA), who originally sought to make the project a reality. However, the Texas Department of Transportation (TXDOT) requested last year that the CRRMA waive its option to develop the project so that TXDOT could bring it to fruition.
The Border Highway West extension will contain many miles of bridge structures, with the majority of the tollway elevated. (TXDOT)

Now, the two parties will partner up on the project, with TXDOT responsible for most of the development and construction and the CRRMA overseeing the design and installation of toll facilities and infrastructure. In addition to the $600 million secured for the project, TXDOT will kick in another estimated $200 million needed to complete the tollway.
This concept image shows the view looking southeast from McNutt Road approaching the elevated Border Highway West tollway. (TXDOT)

Four development teams were shortlisted for the project last October, including two that recently held meetings for subcontractors interested in performing work on the tollway. Rio Bravo Developers, consisting of Fluor Enterprises of Irving, Texas, Ames Construction, Inc., of Minnesota, and Austin Bridge & Road, L.P., also of Irving, held a meeting on January 15, 2014. And Border Highway Mobility Partners, consisting of Walsh Construction of Chicago, Sundt Construction of Arizona, Infrastructure Corporation of America of Tennessee, and Parsons Corporation of California, held a meeting on February 5, 2014.

Monday, February 10, 2014

Weekly Edition, Issue 43

The Weekly Edition, Issue 43 has arrived! Take a look at the newest issue of our Weekly Edition, by clicking HERE. (Note: The newsletter will open in PDF format.)

In this edition:

Don't forget to sign up to be notified when each week's new issue is available. Subscribe below.

Subscribe to our mailing list
* indicates required

Wednesday, October 2, 2013

Closer Look: 2014 Unified Transportation Program

TXDOT’s Program Document Gives Snapshot of Future Projects

The Texas Department of Transportation (TXDOT) programmed hundreds of millions of dollars earlier this year for El Paso’s Border Highway West extension, a project whose total budget could reach $800 million. That’s according to the state’s latest Unified Transportation Program (UTP), approved by the Texas Transportation Commission in June. 

TXDOT uses the UTP to authorize transportation projects for the state, but does not necessarily mean full present-day funding is available for each individual project. Although the Border Highway West has a certain budget in the document, only $300 million has been approved so far.

The nearly 1,200-page UTP includes about 30 pages dedicated to developments in the El Paso District. Timeframes in the report look forward about ten years from the present.

2014

Projects listed for Fiscal Year 2014, which began on September 1, 2013, are spread throughout the city and county. The largest listed in the document is construction of FM 3880 from Alameda Avenue to Interstate 10 in southeastern El Paso County in Tornillo. The new $17.2 million highway will help take traffic to and from the expanded port of entry at the Mexican border, currently under construction.

About $11.5 million is programmed for reconstruction of streets in Downtown El Paso. Another $5.5 million may be used to make improvements to Pan American Drive and Winn Road near the Zaragoza Port of Entry. 

Monday, September 30, 2013

Weekly Edition, Issue 26

The Weekly Edition, Issue 26 has arrived! Take a look at the newest issue of our Weekly Edition, by clicking HERE. (Note: The newsletter will open in PDF format.)

In this edition:

Don't forget to sign up to be notified when each week's new issue is available. Subscribe below.

Subscribe to our mailing list
* indicates required

Tuesday, June 11, 2013

Ring Around the City (Update)

Loop 375 Stacked with Projects

Note: This story was originally published on October 1, 2012. It is being republished with revisions based on project updates.

Years of planning to expand Loop 375 and an infusion of state and regional funding have resulted in several freeway projects occurring all at once around the city with more soon on the way. The Camino Real Regional Mobility Authority (CRRMA) in conjunction with the Texas Department of Transportation (TXDOT) and local officials, has helped many of these projects find funding.
City and transportation officials have coordinated more than $1 billion in projects in the area, but the biggest focus has been on transforming the 375 into a true loop by adding more lanes, constructing main lanes where there are currently only gateways, and expanding the loop westward from its current terminus south of downtown. Officials hope this will alleviate traffic on Interstate 10 as commuters opt for other freeways.

Here is a recap of the ongoing and planned projects along the city's Loop.

Monday, June 10, 2013

Weekly Edition, Issue 10

The Weekly Edition, Issue 10, has arrived! Take a look at the newest issue of our Weekly Edition, by clicking HERE.

In this edition:
  • Ring Around the City: Loop 375 Stacked with Projects (Update)
  • Schuster Roundabout to Open this Fall
  • Country Club Road Construction to Last 560 Days
Don't forget to sign up to be notified when each week's new issue is available. Subscribe below.

Subscribe to our mailing list
* indicates required

Monday, May 6, 2013

$500M Loop 375 Extension

Border Highway West Project May Begin Construction in 2015

Construction on the massive Border Highway West (BHW) extension project could begin in two years, according to the Abbreviated State Final Environmental Impact Statement (EIS) just released by the Texas Department of Transportation (TXDOT). The nine mile project would create a tolled expressway from downtown El Paso, where Loop 375 currently ends, north and west to a point just south of the Interstate 10 at Paisano intersection near Sunland Park.
New ramps will connect the Border Highway with Paisano Drive and Delta Street just east of downtown El Paso.
The abbreviated EIS is an update of the one approved in September of 2012 and highlights any changes that were made to the original. This includes changes to the previously chosen “Alternative 2,” the route that was preferred by the state and announced last year.

Revisions have been made to westbound access to the toll road along the southern edge of downtown as well as changes to the proposed Coles/Paisano interchange. This interchange would give downtown commuters and entrance to Loop 375 eastbound.

The new tolled portion of the expressway will take a 7.1 mile southeasterly route from the west side to downtown. It will run along US 85 (Paisano Drive) from its western terminus and head southeast, then take an eastward turn just past Doniphan Drive. Doniphan currently ends in a dead end west of Racetrack Drive but is extended in the plan to form on- and off-ramps that will provide access to Loop 375.
A schematic design from the state’s Environmental Impact Statement shows the elevated Border Highway West extension in the vicinity of Doniphan Drive and Racetrack Drive.
Border Highway West will then cross the current CEMEX industrial property and take a southward turn at the planned interchange with Executive Boulevard, just west of I-10. The Loop will then run parallel to the Interstate within current TXDOT right of way, on the eastern side of the former ASARCO smelting property.

Weekly Edition, Issue 5

The Weekly Edition, Issue 5, has arrived! Take a look at the newest issue of our Weekly Edition, by clicking HERE.

In this edition:
  • $500M Loop 375 Extension: Border Highway West Project May Begin Construction in 2015
  • University Projects Continue: UTEP Gets Ready for Centennial Plaza Construction
  • Walmart Vote Postponed Again
Don't forget to sign up to be notified when each week's new issue is available. Subscribe below.

Subscribe to our mailing list
* indicates required



Thursday, March 14, 2013

Spur 1966 Project Design to Include UTEP Architectural Style, El Paso Themes

The project to extend Schuster Avenue over Interstate 10 near the University of Texas at El Paso will include aesthetic elements that reflect the school's architecture as well as themes familiar to residents. The extension, called Spur 1966 in homage to the national champion UTEP basketball team, then called Texas Western College, will realign Schuster and connect it to Paisano Drive to the west.

Future Schuster Ave/Paisano Drive intersection, looking east.
Two different sections of the project will include clear aesthetic elements. The first, the pedestrian walkway underneath a proposed roundabout, will have color and architectural elements reflective of the University itself. Bhutanese style columns and embellishments will surround passersby as they travel to and from the adjacent parking lots.

Planned aesthetic improvements to pedestrian underpass at the roundabout.
The second section that will include aesthetic upgrades will be a segment of Paisano Drive north of the future Schuster intersection, at the point where the road transitions from surface level to bridge. A mural of sorts will decorate the concrete wall that supports the road above for several feet. Themes in the concept image include cowboys, mountains, yucca plants, the Rio Grande River, and missions.

Proposed decorative elements along a concrete wall on Paisano Drive.
Construction on the Spur 1966 project could start in spring of 2013 and be completed by fall of 2014. The Texas Department of Transportation hopes to have the environmental assessment ready by summer's end.


Previously:
Schuster Extension May Include Pedestrian Underpass, Roundabout
UTEP Plan Shows Schuster Realignment

Spur 1966 Design Summary (PDF): https://dl.dropbox.com/u/26579627/2013-03-13/2013-03-13-BA-ITEM4.pdf
TxDOT Project Page: http://www.dot.state.tx.us/project_information/projects/el_paso/spur_1966.htm

Tuesday, October 9, 2012

TXDOT to Present Preferred Route for Border Highway West

The Texas Department of Transportation (TXDOT) will present its preferred route for the Border Highway West project at a November meeting. The nine mile project would extend Loop 375 approximately seven miles north and west from its current Downtown terminus, where it would connect to an interchange with Interstate 10 just south of Sunland Park Drive. TXDOT has considered four Alternative routes and will announce that Alternative 2 is the preferred route.

The Preferred Route will travel south of Chihuahuita.
The Preferred Alternative consists of two different sections known as Border A and Rail Yard B. The Border A section travels south and west of the Chihuahuita neighborhood along the Rio Grande and would require only two residential displacements in the preliminary plans.

The Rail Yard B section would run roughly parallel to Interstate 10 on Asarco land, then turn west just before Executive Boulevard. The route would then cross land currently owned by Cemex and turn north again as it approaches Paisano.


According to the upcoming meeting notice, this route "allows for impact avoidance and minimization for a number of resources, fulfills the purpose and need for the project, and provides feasible engineering alternatives. The Preferred Alternative best balances the expected project benefits with the overall effects."

The Preferred Alternative would require acquisition of 42 commercial properties overall, most of which would be along I-10 across from UTEP and along Paisano Drive east of Downtown. The final route may change and is subject to community input.

Meeting Information:

November 15, 2012
4:00 p.m. - Open House
6:30 p.m. - Presentation
University of Texas at El Paso (UTEP)
El Paso Natural Gas Conference Center
Wiggins Way

TXDOT Project Page: http://www.dot.state.tx.us/project_information/projects/el_paso/border_highway_west.htm

Previously:
Loop 375 West Extension Grows Eastward
TxDOT May Fast Track I-10, L-375 Projects

Thursday, June 21, 2012

Loop 375 West Extension Grows Eastward

The scope of the upcoming Border Highway West extension grew by one mile to the east recently when the Texas Department of Transportation unveiled the latest plans for the Loop 375 extension. The project's limits will now stretch from US-54 near Chamizal Park to just south of the I-10/Paisano/Sunland Park interchange. A new interchange has also been included at Coles near Paisano just east of Downtown.

Access mostly blocked south of downtown.
The Border Highway's intersections near the downtown international bridges will be largely limited and mostly blocked off, creating a true expressway feel. Commuters will have to exit east or west of downtown to access the areas, using new interchange ramps that will access Paisano Drive including the new interchange at Coles. Westbound commuters will have an additional exit at Campbell which can be used by those who wish to avoid using the tolled portion of the highway.

Eastward, the State's strategy may be to continue the managed toll lanes currently under construction east of US-54 onto the portion of the Border Highway just added to the project. Plans are already underway to add a toll lane in each direction on Loop 375 from the Zaragoza port of entry up to the America's interchange. In addition, an extra inside lane was included in each direction when the Loop 375 main lanes were constructed from I-10 to Montana, and they remain unused today. If these unused lanes are also changed to managed toll lanes, the State could have managed lanes on Loop 375 from Montana south through the entire stretch of Border Highway, and continued west of downtown to the I-10/US-82/Sunland Park interchange.

The alignment of the highway's 8-mile westward extension has not yet been decided, though it would be surprising to see the State choose the so called Railyard A option considering it would cut right through the historic Chihuahuita neighborhood and require the acquisition of many properties through eminent domain. Border A is the optimal choice; it would run south of the neighborhood and along the Rio Grande River.

Railyard A would cut through historic Chihuahuita.
Further north, the options split again as the tollway reaches the Asarco property. The Railyard B option would basically hug I-10 along the property up to Executive where it would take a turn west and align with Paisano once again. The optimal choice would be Border B as it would run along the same path as Paisano and separate itself from I-10 to truly become it's own highway. Commuters may be less apt to use the tollway if it simply sits to the side of I-10.

The State will present its choice for the tollway's route in a meeting scheduled for November 2012. Additional steps in the process include the environmental study and developing Context Sensitive Solutions, which is the State's goal to tailor the highway to the surrounding community. This includes aesthetics and design elements. TxDOT has become much more serious in recent years in regards to trying to produce visually appealing projects.

TxDOT presented the new plans to City Council on June 19, 2012, and to the public at a meeting at UTEP on June 20.

Border Highway West project website: http://www.txdot.gov/project_information/projects/el_paso/border_highway_west.htm

Previously:
TxDOT May Fast Track I-10, L-375 Projects